- Highways
- 13 Jan 2026
Banbury Railway Station is a key transport hub in Oxfordshire, serving thousands of passengers daily. To promote sustainable travel and improve connectivity, Oxfordshire County Council selected M Group Highways civils projects team to deliver a programme of highways upgrades around the station.
Client: Oxfordshire County Council
Duration: November 2024- ongoing
The scheme was split into two work packages:
- Main highways improvements- road layout changes, pedestrian/ cycle links and new bus facilities.
- Accommodation works- adjustment for Network Rail and Chiltern Railways operations.
As part of the works, our team were tasked in delivering several improvements, including:
- Extending Tramway Road to connect with Station Approach via a new roundabout.
- Creating dedicated pedestrian, cycle, bus and taxi links between the station forecourt and Tramway Road.
- Building new footways, cycleways and crossings to improve station access.
- Restricting general vehicle access to parts of Station Approach.
- Reconfiguring car parking layouts and introducing new access points.
- Installing new bus stops along Tramway Road and Station Approach Road.
- Upgrading lighting and landscaping for safety and aesthetics.
Our team has worked to successfully deliver highways improvements within phase one and two. Working to a high standard, we’ve ensured safety, sustainability and minimal disruption to station operations.
A phased approach, has allowed our team to progress the highway improvements while adapting to unforeseen challenges, such as:
- Redesigning on the move- Due to unforeseen issues, design was reworked without halting progress on other areas.
- Managing asbestos safely- Soil sampling revealed asbestos in the ground, leading to continuous air monitoring and a strict watching brief throughout the build.
- Protecting heritage- Archaeological watching briefs were put in place due to the historic footprint of the Britannia Works building, which had significant local interest.
- Responding to discoveries- A Victorian culvert was found during pipe run installation, as well as old track uncovered withing ducting works.
- Sustainable design features- Installed pollution controls measures to protect local waterways.
In June 2025, phases one and two were completed, delivering a new roundabout, Tramway Road extension and connection to Station Approach South.
Following unexpected discoveries in the ground during the first phases of construction, we now expect to finish work in December 2025. The timeline may change if we have to work around any additional discoveries, poor weather conditions or other planned work in the area.